OpSpot Blog

Industry Best Practices

Commercial Fit-Out Schedule Template: The Trade Sequence, Week by Week

29 October 2026

Commercial Fit-Out Schedule Template: The Trade Sequence, Week by Week

Published: October 29, 2026 | Reading Time: 4 minutes | Author: OpSpot Team

Short answer: a commercial fit-out runs in a predictable order: strip-out, set-out and wall framing, services rough-in in the ceiling and walls, ceiling grid and wall sheeting, setting and painting, joinery and glazing, ceiling tiles and fit-off, floor finishes, then testing, cleaning and handover. Below is a six-week example programme for a small office tenancy, the hold points that stop rework, and a template you can copy.

This is a typical sequence for a small office fit-out. Your programme depends on the size of the job, approvals and lead times, so adjust the durations to suit.

Before day one

  • Approvals: confirm what the job needs, for example landlord and building manager approval, and any building approval for the work.
  • Long-lead items: order joinery, glazing, doors and hardware, and any mechanical units before you start. They usually set the pace, not the trades on site.
  • Subcontractors: collect licences, insurance and SWMS before anyone starts (see our subcontractor pre-qualification checklist).
  • Book the trades: lock in each trade's dates now, then confirm a week out.

Six-week example programme

WeekStageTradesTypical work
1Strip-out and set-outDemolition, electrician, carpenterMake services safe, strip out old partitions, ceilings and floor coverings, mark out new walls
2Framing and ceiling rough-inCarpenter or partition installer, mechanical, fire services, electrician, dataWall tracks and studs; ductwork, sprinkler changes, cabling and data runs in the ceiling
3In-wall rough-in and sheetingElectrician, data, plumber, plastererCabling and plumbing in the walls, then plasterboard once they're checked; ceiling grid goes up
4Setting, painting, joineryPlasterer, painter, joiner, glazierSet and sand, first coats of paint, kitchenette and reception joinery, glass partitions and doors
5Ceilings, fit-off, floorsCeiling fixer, electrician, data, mechanical, plumber, floor layerCeiling tiles, lights, diffusers and sprinkler heads; power, data and plumbing fit-off; carpet tiles and vinyl
6Testing, finishing, handoverMechanical, fire services, electrician, painter, cleanerTesting and commissioning, paint touch-ups, signage, builders clean, defects walk, handover documents

Hold points that stop rework

  1. No plasterboard until the in-wall services are in and checked. Cutting into new sheeting to add a power point costs more than waiting a day.
  2. No ceiling tiles until everything above the ceiling is finished, including mechanical, sprinklers, cabling and any inspections.
  3. No carpet or vinyl until painting and ceilings are done. Floor finishes go in after the messy trades leave.
  4. No handover without the paperwork: test results, certificates, warranties and as-built information for the client.

Template: copy this into your schedule

TaskTrade (job type)StartDaysDepends onCrew or subcontractorNotes
Make services safeElectricalWeek 1, day 11—

Strip-outDemolitionWeek 1, day 13Make services safe
Waste bins booked?
Set-out of new wallsCarpentryWeek 1, day 41Strip-out

Wall framingPartitionsWeek 2, day 14Set-out

Ceiling services rough-inMechanical, fire, electrical, dataWeek 2, day 15Strip-out
Coordinate access in the ceiling
In-wall rough-inElectrical, data, plumbingWeek 3, day 12Wall framing
Check before sheeting
Wall sheetingPlasteringWeek 3, day 33In-wall rough-in

Ceiling gridCeilingsWeek 3, day 33Ceiling services rough-in

Set and paintPlastering, paintingWeek 4, day 15Wall sheeting

Joinery and glazingJoinery, glazingWeek 4, day 33Set and paint
Long-lead items
Ceiling tiles and fit-offCeilings, electrical, data, mechanical, plumbingWeek 5, day 14Joinery, set and paint

Floor finishesFlooringWeek 5, day 42Ceiling tiles, painting

Testing and commissioningMechanical, fire, electricalWeek 6, day 12Fit-off

Clean, defects and handoverCleaning, all tradesWeek 6, day 33Testing
Handover documents

Running this schedule in OpSpot

  • A booking for each block of work, with its dates, job type and the people attending. On a multi-day booking you choose who attends on each day (see Scheduling crews with the calendar, planner and Gantt).
  • The planner's Classic view shows each job type as its own row, so it's obvious if the ceiling crew is booked before the electrician's rough-in is finished.
  • See who's free before you book: choose a job type and OpSpot lists every staff member and subcontractor who does that work, with four weeks of availability (see Crew and subcontractor availability by trade).
  • Reminders go to the workers, the client and the project manager, at the times you choose.
  • Share a read-only Gantt chart with the client through a link that can expire, or export the planner to PDF for a site meeting.

FAQ

What order do trades go in on a fit-out? Strip-out, set-out and framing, services rough-in, ceiling grid and wall sheeting, setting and painting, joinery and glazing, ceiling tiles and fit-off, floor finishes, then testing, cleaning and handover.

How long does an office fit-out take? Our example is six weeks for a small office tenancy. Larger or more complex fit-outs take longer, and approvals and long-lead items such as joinery and glazing often decide the finish date.

Should I run my fit-out schedule in Excel? A spreadsheet works for one job and one scheduler. Once you're running several jobs with the same trades, you need to see who's free and avoid double bookings (see OpSpot vs spreadsheets).

Can my client see the schedule? In OpSpot, yes: share a read-only Gantt chart for their project. It shows the job number, not your other jobs or internal notes.

Related guides

Book a Demo